Our house- Progress Images Here is a chronological sequence of how it is going… MAY 2015 ORIGINAL LOT , THEN CHOPPED DOWN AVOCADO AND GRAPEFRUIT TREES. LAST, OUR DAUGHTER FEEDING THE CHIPPER ON AUGUST 2015. AUG 22 2015- CLEARED LOT SEPTEMBER 2015 GRADING STARTED SEPT 13 2015 GRADING COMPLETED NOV. 6 TRENCHES OUTLINING THE EXTERIOR HOUSE WALLS NOV. 21 STEEL GRID TO PREPARE FOR CONCRETE SLAB NOV. 24 POURING CONCRETE SLAB MEN AT WORK LEVELING CONCRETE NOV. 29 CONCRETE SLAB POURED AND SET DEC. 2 FRAMING BEGUN FRAMING- BACK SIDE OF THE HOUSE DEC. 8 FRAMING CONTINUES DEC. 15 TRUSSES GO UP! BACK SIDE OF THE HOUSE WITH TRUSSES UP DEC 17 ROOF ALMOST COMPLETE DEC 19 BACK SIDE – ROOF COMPLETE DEC 31 ROOF COVERED WITH TAR PAPER AND WINDOWS IN BACK SIDE , WINDOWS IN JAN. 14 2016 ROOF TILES PILED UP AND EXTERIOR PREP’D FOR PLASTER Share this:TwitterFacebookLike Loading...