Our house- Progress Images

Here is a chronological sequence of how it is going…

MAY 2015

ORIGINAL LOT , THEN CHOPPED DOWN AVOCADO AND GRAPEFRUIT TREES. LAST, OUR DAUGHTER FEEDING THE CHIPPER ON AUGUST 2015.
20150520-House_May2015
AUG 22 2015- CLEARED LOT

 

20150902_160759
SEPTEMBER 2015 GRADING STARTED

 

20150913_115939
SEPT 13 2015 GRADING COMPLETED

 

20151106_132037
NOV. 6 TRENCHES OUTLINING THE EXTERIOR HOUSE WALLS
20151121_162506
NOV. 21 STEEL GRID TO PREPARE FOR CONCRETE SLAB
20151124_091013
NOV. 24 POURING CONCRETE SLAB
20151124_090421
MEN AT WORK LEVELING CONCRETE
20151129_114552
NOV. 29      CONCRETE SLAB POURED AND SET
20151202_114549
DEC. 2 FRAMING BEGUN
20151202_120146
FRAMING- BACK SIDE OF THE HOUSE
20151208_120829
DEC. 8 FRAMING CONTINUES
luminaria_121515-a
DEC. 15 TRUSSES GO UP!

 

luminaria_121515-b
BACK SIDE OF THE HOUSE WITH TRUSSES UP
20151219_161643
DEC 17   ROOF ALMOST COMPLETE
20151219_155442
DEC 19   BACK SIDE – ROOF COMPLETE

 

20151231_110629
DEC 31 ROOF COVERED WITH TAR PAPER AND WINDOWS IN
20151231_110737
BACK SIDE , WINDOWS IN

 

20160115_103216
JAN. 14 2016 ROOF TILES PILED UP AND EXTERIOR PREP’D FOR PLASTER

 